Written by The Bridge Lady (Regina)

Links Bridges: The Wedding Bridge

Every bridge project we ever do has its own interesting story. This story is about a gentleman who needed a bridge to access his man-made island so his daughter could have her wedding ceremony on the island. The interesting twist to this story is how his insistence on a certain bridge feature led to an innovation that is now an integral part of the Links Bridges’ menu offering.

The requirement was for a 35’ long simple arched bridge – The Woody without the curbs. After checking several other options, the customer decided Links Bridges’ Woody was the best choice. When we provided the initial drawing set, he was surprised – and disappointed – to see that the bottom of the bridge beams were flat and it was only the deck and top of the beams that were arched.

That style of beam had been designed by our engineers as the optimal for structural qualities. It had always been in our plans to find the right formula to move to completely arched beams and we had already done a lot of the testing – just not enough to ‘finish the job’. This gentleman’s requirement for that feature was all the impetus that we needed to get moving.

Sophisticated fiberglass production requires the fabricator to design/engineer the style of structural cloths that will achieve the structural, tensile, flexibility and other qualities for the end product. Our engineers and technicians resumed their calculations and testing and actually came up with a formula for fully arched beams that even out-performed its ‘theoretical’ capacities.

We are extremely happy with the result and the nice clean look it gives the bridge. We are now incorporating this beam design into all of our arched bridges where the beam is visible. Besides what we think is a nicer ‘look’, this also provides the advantage of increased clearance in the event of minor flooding.

The ‘Wedding Bridge’ was delivered on time and installed by Links Bridges’ field team. There were happy endings all around.
I am sure that we can say confidently the buyer’s expectations were exceeded. Like all of our Woody-style bridges, they are 100% fiberglass but you really can’t tell them from ‘real’ wood. We even got a picture of the wedding party – a very good looking group.

Stay tuned for our continuing series of Bridge Stories. More to come…

residentials bridge
Written by The Bridge Lady (Regina)

Bridge Stories

There is a story behind every bridge we have ever made. We like to share these bridge stories because we hope that you will find them interesting and will want to work with us to make your own ‘bridge story’.

There is no shortage of material for the Bridge Stories.  Every project involves some combination of people, places and challenges.  We have been fortunate to meet and deal with some outstanding people as we have taken on more and more bridge projects.

It has also given our team the opportunity to do business in many interesting places in North America.  This is its own learning experience and it has a value that is hard to measure.

On the technical side, our business is committed to innovation.  This means our engineers and technicians are always be dealing with new ‘first-time’ challenges.  That’s a good thing.  It pushes all of us to constantly learn and improve and it makes us all better for it.

These ‘bridge stories’ sometimes intentionally omit names of people and their organizations.  This is out of respect for the privacy interests of our valued customers.

Sirocco Golf Club in Calgary, Alberta
Written by The Bridge Lady (Regina)

Bridge Renewal

This bridge story is about what we consider to be one of the most important innovations that will impact on what we can offer for golf courses, municipalities and other organizations with bridges over the next few years.  It is about how we have developed a method to manufacture a simple fiberglass ‘skin’ (in a wood or other finish) to make old bridges ‘new’ and extend their lives by decades in some cases.

We have to give credit where it is due and acknowledge that this innovation was developed to respond to needs identified by some wonderful people at the Sirocco Golf Club in Calgary, Alberta.  They were the first to push us in this direction.  We first heard from Dean Clarke the Superintendent at Sirocco and later from Tom Ellison the General Manager at Sirocco.

They identified that they had 9 bridges that were still OK but going relatively fast.  The substructures were fine but the decks were on the verge of needing replacement.  Working together, we came up with the idea of smoothing the decks to the point where we could bond and seal a thin, custom-manufactured fiberglass skin (in a wood finish) to the existing decks.  The process also involves sealing the joints of the ‘skins’ – which were made in sections to custom-fit over the entire deck.

This achieves a number of really important things:

  • The bridge looks ‘new’. Everything you can see is in fact new and the remainder is hidden.

  • The deck is now a low-maintenance, long-lasting fiberglass surface.

  • The deck and substructure are now sealed from any further moisture or UV exposure or penetration. The deterioration of the substructure will now virtually stop.

RenewalSirocco Golf Club in Calgary, Alberta

Pre & post coating shows the dramatic difference between the ‘before’ and ‘after’.

We are now working with the Sirocco team to complete the process on their remaining bridges.   At the same time, we are extended the offer for this product and service to the broader market as our research tells us that there is substantial potential for this to be a huge benefit to many of our customers to allow them to save a lot of money.

 

Carlteon Place
Written by The Bridge Lady (Regina)

In a hurry? What could go wrong?

This bridge story is a tribute to the determination of Links Bridges’ Installation team and as well to the precision of our Manufacturing team.  Without both of these, this story would read differently.

Links Bridges was contracted by a public housing organization to provide a replacement for a bridge that connected a parking lot to the 2nd floor entrance of a multi-unit housing building.

The key to success, aside from providing a great, long-lasting, low-maintenance bridge, was to minimize the down-time between bridge removal and bridge replacement.  The bridge was a key entrance and egress for the residents who would suffer major inconvenience if they lost use of the bridge for more than a day.

It was determined, based on historical engineering data, that the existing foundations could be re-used.  Links Bridges was supplying a fiberglass bridge which was considerably lighter than the existing steel bridge/concrete deck previously installed.  It was also important to fit the bridge perfectly into an existing building alcove so that building structures were not impacted and the interior floor/deck interface were on the exact same level.

rotten wood

Existing Steel Bridge – 40’ long

The bridge was made and completely assembled so that it could be installed in 1 piece to minimize down time between bridges.  The installation date was set and equipment and personnel scheduled to come in to remove and demolish the existing bridge.  The plan was for ‘same-day’ removal and installation.

As it turned out, events affected plans.  The scheduled day turned out to the coldest day of the winter and a heavy snowfall made things even more difficult.  Our hardy crew would not be deterred and work proceeded.

The real problem happened when the old bridge was lifted out, we discovered damage to one of the concrete footings.  The damage was such that the bearing points for the new bridge were compromised.

Carlteon Place

We quickly got the Engineering Team involved and they designed a solution that involved anchoring steel angles into the (uncompromised) sides of the foundations to provide a new bearing surface for the bridge beams.  Our daylight hours were quickly disappearing and lifting a 40’ bridge into a tight space in dark, snowing, sub-zero conditions is never a good plan.  Besides, we still needed to locate a steel fabricator who would be willing to stop what they were doing and cut some angle steel to the sizes that were required.

With a bit of luck, charm and determination, we managed to get the steel that same night.  Throughout the next morning and afternoon our hardy crew suffered through extreme conditions to get these installed to provide a bearing platform for our bridge beams.  With daylight quickly fading, our crane started to lift the bridge into place.

Thanks to the precision work of our manufacturing team, the bridge was a perfect fit for the tight space.  Within an hour the bridge was anchored and ready for use.  This important access for the building residents was restored.

This picture was taken the morning after installation.  Snow and sub-zero temperatures made things a little more difficult.

GIS2017
Written by The Bridge Lady (Regina)

“Inside The Ropes” at Golf Industry Show (GIS2017)

Links Bridges is pleased to announce a partnership with the 2017 Golf Industry Show – (GIS2017).

This year’s GIS is in Orange County Convention Center in Orlando, Florida from February 4 to 9.

A new feature at the 2017 GIS is ‘Inside the Ropes’.  The Golf Course Builders Association of America (GCBAA) and other sponsors are teaming with GIS to create a 9,000 square foot area featuring Golf Course amenities.  Links Bridges is one of the key sponsors.

‘Inside the Ropes’ is a must-see at the 2017 GIS.  Links Bridges will provide an actual golf course bridge ‘Inside the Ropes’.  The bridge will be Links Bridges’ ‘Woody’ model – our most popular golf course bridge.  The ‘Woody” is made of 100% fiberglass and has a very authentic wood finish.

 

This is a unique opportunity for Golf Course Operators to check out the look and feel of a Fiberglass Golf Course bridge.   Wood bridges rot, steel bridges rust – both require maintenance.  Fiberglass bridges outlast all other bridges.  They  require no maintenance and retain their natural looks for decades.

Be sure to visit ‘Inside the Ropes’ and come see Links Bridges at Booth # 1612 at the 2017 GIS in Orlando.

The Wood bridge at GIS2017 is 15 feet by 6 feet with ramp in both sides. Would you like to take it home with you?

 

 

100% Fiber Glass Bridge
Written by The Bridge Lady (Regina)

Links Bridges reaches milestone in Carleton Place!

Links Bridges achieved another milestone this week with the installation of a bridge serving a residential complex.  The bridge connects a parking lot to a building entrance on the 2nd floor of the building at Carleton Place, Ontario residential complex.

The project involved removal of an existing steel bridge which after 25 years of service had severe rust.  The replacement bridge, from Links Bridges Composite Series, was made with FRP (Fiber Reinforced Plastics) beams and decks.  The guard rail was made entirely of HDPE (High Density Poly-ethelene).

This bridge will last for decades.  There are no materials that will rot, rust or require any kind of painting or coatings to maintain the look of the bridge.  The management of the building initially became aware of the Links Bridges alternative from 2 bridges that Links Bridges supplied earlier in 2016 to the nearby community of Smiths Falls, Ontario.

The project was not without its challenges.  To prepare the bridge, the existing bridge details were carefully measured incorporated into the bridge design details.  There was no margin for error.  At each end the bridge had to match existing elevations including at the building entrance where the bridge deck needed to be exactly flush with the door jamb.  There were existing fences, retaining walls and abutments that had to be accommodated if this bridge was going to fit.

The initial plan had been to remove the old bridge and put in the new bridge all in the same day.  Unfortunately, when the old bridge was removed, it was discovered that the existing abutments – which were to be re-used for the new bridge – had suffered some erosion that wasn’t visible until the bridge was removed.

An immediate solution was required because there were residents of the building with access challenges who were reliant on this bridge to come and go.  The Links Bridges’ engineer assessed that the base of the abutments was sound but the integrity of the top surface of the abutments were compromised.

The engineer decided against a ‘concrete’ solution primarily because the temperature was well below freezing levels and not a good situation for concrete to properly cure.  The engineer designed a solution that involved anchoring steel angles to the (uncompromised) side of the abutment.

The Links Bridges team had the required steel fabricated and coated over night.  The next day the team worked in extreme cold conditions to get the abutments ready to receive the bridge.  By mid-afternoon, the bridge was lifted into place.   Everything fit perfectly and by late afternoon, the bridge was fully operational.

 

Links Bridges
Written by The Bridge Lady (Regina)

Restore Your Bridge Back to Life

We live in a disposable era, where the moment things break we either leave them that way (and promise we will fix them next weekend) or we replace them entirely, scrapping otherwise functional materials in exchange for a quick fix. Our mission at Links Bridges is to save our customers their time, their money, and their sanity. We have created a line of sustainable, eco-friendly bridges for municipalities, golf courses, and residences that don’t need to be fixed or replaced every few years. Additionally, we strive to replace the wastefulness in the landscaping industry by encouraging and providing services to accommodate bridge restoration and renewal.

With Links Bridges bridge restoration, our clients get to experience both an aesthetic and functional ‘new’ bridge at a fraction of the cost. Here is how:

First, consider that any bridge has 3 main components:

  1. Foundations/Abutments
  2. Beams
  3. Deck/Rails

It is often the case that the foundations and beams are still in great shape long after the deck has deteriorated.  This is particularly true for steel beam/wood deck bridges.

Our team of expert bridge designers and installers have perfected the art of bridge restoration, whereby, rather than replace the entire bridge when the deck needs replacement, Links Bridges can custom fabricate a new FRP deck.  Done properly, it can provide all of the benefits – including the look – of an entirely ‘new’ bridge. The best part is that this can all happen at a fraction of the cost of a new bridge.

The Links Bridges crew recently worked with the Sirocco Golf Club in Alberta on a successful restoration project.  The pictures below show the result.

Before:

links1

 

After:

links2

 

If your municipality, residence, or golf course has an older bridge that could use some tender love and care, contact our bridge experts at Links Bridges today for a free consultation on how to restore and revitalize your bridge. Whether your bridge runs through a golf course, a park, a trail, your backyard or otherwise, we can help bring it back to life. Contact us at info@linksbridges.com or call us at 888-444-0277.

Written by The Bridge Lady (Regina)

Restore Your Bridge Back to Life

We live in a disposable era, where the moment things break we either leave them that way (and promise we will fix them next weekend) or we replace them entirely, scrapping otherwise functional materials in exchange for a quick fix. Our mission at Links Bridges is to save our customers their time, their money and their sanity. We have created a line of sustainable, eco-friendly bridges to municipalities, golf courses and residences that don’t need to be fixed or replaced every few years. Additionally, we strive to replace the wastefulness in the landscaping industry by encouraging and providing services to accommodate bridge restoration and renewal.

With Links Bridges bridge restoration, our clients get to experience both an aesthetic and functional ‘new’ bridge at a fraction of the cost. Here is how:

First, consider that any bridge has 3 main components:

Foundations/Abutments

Beams

Deck/Rail

 

It is often the case that the foundations and beams are still in great shape long after the deck has deteriorated. This is particularly true for steel beam/wood deck bridges.

Our team of expert bridge designers and installers have perfected the art of bridge restoration, whereby, rather than replace the entire bridge when the deck needs replacement, Links Bridges can custom fabricate a new FRP deck. Done properly, it can provide all of the benefits – including the look – of an entirely ‘new’ bridge. The best part is that this can all happen at a fraction of the cost of a new bridge.

The Links Bridges crew recently worked with the Sirocco Golf Club in Alberta on a successful restoration project. The pictures below show the result.

If your municipality, residence or golf course has an older bridge that could use some tender love and care, contact our bridge experts at Links Bridges today for a free consultation on how to restore and revitalize your bridge. Whether your bridge runs through a golf course, a park, a trail, your backyard or otherwise, we can help bring it back to life. Contact us at info@linksbridges.com or call us at 888-444-0277.

Written by The Bridge Lady (Regina)

The Golf Inc Strategies Summit

All about the The Golf Inc Strategies Summit 2016

The team at Links Bridges is pleased to be a part of this weekend’s Golf Inc Strategies Summit. The summit is located at the breathtaking Omni Barton Creek Resort & Spa in Austin, Texas. Regina, our very own Bridge Lady, has travelled all the way to Texas, with her camera and questions in hand as she records her meetings with many of the golf industries greatest influencers, aficionados and players.

 

Meeting New Friends

We were honored to meet with Marko Kaldoja from Pärnu Bay Golf Links who represents two golf courses and describes the Omni Barton Golf Course as “fantastic…with really great views” and is eager to “hear great ideas, share some knowledge and learn a thing or two that we can implement back home”. His courses have concrete bridges and is eager to meet with Regina to learn more about Links Bridges’ unique and sustainable fiberglass bridges.

 

Chris Karamitsos is from Tampa, Florida of Millichap National Golf Resort Properties Group. When asked why he is here he tells me his hope is to “meet with some industry professionals and tell them about what is going on with the golf transaction market”.

 

Lessons from the Keynote Speakers

On day two, we enjoyed the opening Keynote presentation about predicting Golf’s Future with Eric Affeldt, the CEO of ClubCorp, Dana Garmany, the CEO of Troon (who teaches us all the tricks of the trade when it comes to golf course management) Peter Hill, the Chairman & CEO of Billy Casper and Jim Hinckley, the CEO of American Golf (who knows the industry inside and out as a reputable executive in the course management and ownership industry).

Here are some of our favorite panelist insights and predictions that they presented when they were asked the burning question at this year’s Summit:  “What would you say is going to happen here in the next five years?”

  • The population playing golf will remain stable and people will have much easier access to golf courses and resorts with the varying technological advancements in the industry.
  • The consumer will have more and more choices on where to play golf, how to set up your tee times (online and offline) and the consumer can make decisions more last minute than in the past.
  • Food and Beverage services, special services are becoming more important to each course
  • It is changing from a mere athletic endeavor to an entire experience.
  • Initiations fees will remain low, as people are hesitant to spend a lot of money right now.
  • In the last six months, corporate travel has reached an all-time low, and this means there may be a decrease in corporate related golf travel in the near future.

With a schedule filled to the brim with inspirational speakers, educational sessions and networking events, we expect to learn. To stay up to date on our video blog updates from Regina, Like Us On Facebook. Learn more about the Golf Inc Strategies Summit online at http://www.golfincmagazine.com/strategies-summit/

 

Here are some photos from the summit:

img_0756 img_0755  14352069_1791158157833016_5036938371115827847_o 14362445_1791159927832839_6107033060271912721_o 14372418_1791159497832882_3839583747312855392_o14322633_1790690874546411_4938748186894254563_n

 

 

Save

Written by The Bridge Lady (Regina)

Top 5 Reasons to Choose “The Side Beamer” Bridge

The Side Beamer Bridge is a classic bridge design using our space frame engineering technology. This bridge can span up to 150′ in a flat or arched design. It provides a much more contemporary appearance compared to the more ‘industrial-looking’ big beam bridges. Its appearance can be enhanced with any of the Links Bridges’ Composite Series designs as the deck and guard rails.

Here are our top five reasons to choose the Side Beamer Bridge from our collection of bridge styles and designs.

Long-lasting

The Space Frame has a proprietary coating which outperforms galvanizing by a factor of 3 to 1. The remainder of the bridge is 100% FRP which will retain its structural integrity and appearance for fifty years or more.

Low-Maintenance

The Side Beamer bridge will provide many, many years of rust-free functionality. The side beam, deck and guard rails can last decades with low to no maintenance requirements. Relative to a traditional galvanized steel structure, this bridge is exceptionally maintenance free.

Easy Installation

The Space Frame support is lightweight relative to traditional steel beams. The deck and guard rail materials are far lighter than wood, and this means the installation of the Side Beamer Bridge requires less healthy equipment for installation and smaller abutments.

Turn-Key Solutions

Our team will provide engineering on the bridge and foundations, alongside all of the necessary parts to assemble the bridge, timely delivery to your bridge construction site and full turn key installation. Choose from custom lengths up to 150’ and widths up to 24’, custom branding options and eco-friendly materials.

Affordable

The Side Beamer Bridge from Links Bridges is a cost-effective design when compared to other enclosed bridges and building connectors.

Are you ready to install your Side Beamer Bridge? Contact our team and we will provide a detailed, customized quote within three business days.