BEFORE YOU START

Bridge planning & installation guide

The most expensive mistakes are made long before the bridge arrives. Here is how to size your bridge, choose a foundation and get it installed.

Talk it through: 1.888.444.0277
Newly installed Links Bridges 100% Fiberglass Bridge with post and rail, telehandler in the background
+2–3 ft Size the bridge longer at each end so foundations sit well back from the water's edge.
80%+ of our installations use helical piles, our preferred foundation.
< 1 day Typical install with helical piles, piles included. Setting the bridge itself takes under 2 hours.
PART 1

The most common (and costly) mistake

Sizing the bridge so its ends land at, or very close to, the edge of whatever it spans.

✕ Too short: ends at the water's edge
Retaining-wall abutments, heavy excavation, possible coffer dams and permits.
✓ Right-sized: 2–3 ft past each edge 2–3 ft2–3 ft
Helical piles on undisturbed ground; the waterway is left untouched.

Why it drives up cost

It forces the most expensive foundation. Ends at the bank usually need concrete abutments that double as retaining walls, so excavation is at its maximum.

It draws regulatory attention. Disturbing a waterway can bring regulators who require temporary coffer dams while the foundation is dug, formed and poured.

It makes the job slower and messier. More digging, more concrete, more time and more site damage.

The fix: add 4–6 feet to the span

Make the bridge 2 to 3 feet longer at each end. The water stays undisturbed, and faster, less expensive foundations like helical piles become possible.

PART 2

Foundation options

Site and bridge conditions can rule some of these out, so please confirm your choice with us.

Option Best suited to Relative cost Foundation time
Re-use existing foundationsReplacing an old bridge on sound foundationsLowestMinimal
Helical piles PREFERREDMost sites; over 80% of our installationsLowSame day as bridge
Concrete slabAreas with no ground frostLow2–4 days
Drilled piersConcrete where frost depth or soils require itHigher2–4 days
Spread footingsExtreme lateral (hurricane wind) or uplift (intense flooding) loadsHighest2–4 days
Pre-cast concrete blocksSmall residential bridges, DIYLow1 day
Concrete timing covers excavation, forming, pouring and curing: at least 2 days, usually 3–4. Concrete costs vary widely by site.
Replacement Links Bridges 100% Fiberglass Bridge set on its existing foundations at a golf course

Re-using existing foundations

The most cost-effective option when you are replacing a bridge. Every Links Bridges 100% Fiberglass Bridge is custom-made, so we build to the foundations already in the ground. Send us measurements and photos early so we can confirm they are suitable.

Concrete foundations

The most familiar choice. Spread footings are large blocks with a wall on top, rarely needed for our bridges. Drilled piers are two or more cylinders per end, tied by a poured cap. A slab is poured at each end where frost isn't a factor. Pre-cast blocks suit small DIY bridges, set level on crushed stone and buried for uplift.

Concrete foundations need a Professional Engineer. The rebar has to be designed for the site's soils, frost line and loads. Expect a geotechnical (soils) report.

Helical piles PREFERRED

Steel shafts with a screw-like helix, driven into the ground. We almost always recommend them, and over 80% of our installations use them.

Installed helical piles with steel caps, ready for the bridge

Why we recommend helical piles

Lower cost

Concrete costs are hard to predict and, in our experience, almost always higher. Sometimes considerably.

Faster install

Done in less than a day, piles included. There is no cure time. Concrete needs at least 2 days, usually 3 to 4.

Less site damage

1–2 ft of digging at each pile, all of it put back. A mini-excavator instead of 35-ton concrete trucks.

No soils report

Bearing capacity is read pile by pile as it's driven, so a geotechnical report generally isn't needed.

PART 3

Installation with helical piles

Steps may vary with site conditions. Where they differ, your Technical Package governs.

Pile count

One pile per beam at each end of the bridge.

Bridge widthBeamsPiles
6 ft24
8 ft36
10 ft48

Materials & equipment

Helical pilesTypically 7 ft long × 3 in diameter; thicker piles or extensions for unusual soils or loads
Pile caps (one per pile)12 × 12 × ½ in galvanized steel, four 3/8 in holes 2 in from the corners
Anchor hardware3/8 in bolts with washers and nuts, four per pile cap
Fiberglass end platesSupplied with the bridge, plus Tapcon® screws, four per beam
EquipmentMini-excavator with helical drive; telehandler or crane and straps rated for the bridge weight; level; drill
Before you dig: have underground utilities located (call 811 in the U.S.) and confirm any required permits. Lifting should be done by a qualified equipment operator.
1

Install the helical piles

Mark each pile from your Technical Package: centered under a beam, 6 in from the beam end. Drive the piles; the top-of-pile elevation sets the bridge height, so check it against the plans. Watch back-pressure as each goes in, and add an extension if capacity is short at 7 ft. Level the tops, set a cap on each and check it with a level.

Crew driving a helical pile beside a pond
2

Place the bridge

Rig it with straps rated for its weight, tucked under the curbs where the side-rail blocking leaves space, for a balanced load. Lower it so the final 1 ft of each beam end bears on its pile cap; there are a couple of inches of margin. Once foundations are ready, placing and anchoring the bridge usually takes no more than a couple of hours.

Telehandler lifting a Links Bridges 100% Fiberglass Bridge by its beams into place
3

Secure the bridge

Using the cap's pre-drilled 3/8 in holes as a guide, drill up into each beam. Bolt every beam to its cap with a 3/8 in bolt, washer and nut. Then fit the supplied fiberglass end plates over the beam ends: 4 Tapcon® screws per beam, 2 on each side, pre-drilled.

4

Final checklist

  • Piles at required bearing capacity and top-of-pile elevation
  • Caps level and centered under each beam, 6 in from the end
  • Final 1 ft of each beam end bearing on its cap
  • Four bolts, washers and nuts tight at every cap
  • End plates fastened at both ends, 4 screws per beam
  • Rigging removed; deck and rails inspected
  • Soil returned; site backfilled and graded

Planning a bridge project?

Call us before you finalize the span, the foundations or the schedule. The more we know about your site, the better we can help you find the most cost-effective path.